ExxonMobil, QatarEnergy delay $10 billion Golden Pass LNG following Zachry bankruptcy
The companies agreed other contractors could finish work on Golden Pass last month, paving the way for a restart after several setbacks this year. The new schedule means the 18 million-metric-ton-a-year facility, one of the country’s biggest, will begin operations about six months later than the previous plan, Exxon Chief Financial Officer Kathy Mikells said during an interview.